燃煤电厂烟气脱硝前期工作要点
韦飞,惠润堂
(国电科学技术研究院,江苏 南京 20031)
Main points of earlier stage works for DeNOx of coal-fired power plant
WEI Fei , HUI Run-tang
(Guodian Science and Technology Research Institute, Nanjing 210031, Jiangsu Province, China)
ABSTRACT: The State will be strictly controlled nitrogen oxide emissions during the Twelfth Five-Year Plan, this article introduces the major coal-fired power plant flue gas denitration preliminary work, and previous work points to a simple analysis of precautions to avoid the emergence of denitrification gas engineering construction desulfurization of various defects, in order to ensure post-denitrification construction quality and performance assurance.
KEY WORDS: flue gas denitration;denitration technology ;preparation work;problem;operation rate
摘要:国家十二五期间将严格控制氮氧化物的排放,本文主要介绍了燃煤电厂烟气脱硝主要前期工作,并对前期工作中的要点注意事项进行简单分析,避免脱硝工程建设中出现烟气脱硫中的各种弊端,以保证后期脱硝工程建设质量和性能保证。
关键词:烟气脱硝;脱硝技术;前期工作;注意问题
1 引言
根据火电厂未来增容的预测和燃煤增量的预计,“十二五”期间火电厂氮氧化物的排放总量将预计由2010年的1050万吨增加到1200万吨左右,国家“十二五”纲要明确提出“十二五”期间氮氧化物减排量达10%。目前《火电厂大气污染物排放标准》修订版预计将在年底颁布,氮氧化物排放浓度主要为100mg/Nm3。在环保压力以及酝酿中的脱硝电价补贴利益的共同驱动下,火电厂脱硝工程的建设将急剧膨胀。
预计“十二五”期间火电机组烟气脱硝工程主要可分为以下三个部分:(1)现有老机组新增脱硝装置,基本要在2014年7月1日前完成改造;(2)“十一五”期间已上脱硝装置,目前由于氮氧化物的排放标准提高,均面临增容改造;(3)新建火电机组需同步投建脱硝装置。
2 烟气脱硝前期工作
|